PN65 progress report

A short progress report on PN65 and PN66, seen here in dry-dock together. Launching date is fast approaching for PN65, and she will float out on 20th January. On the 23rd January the keels will be laid for PN67 and PN68.



The photo shows PN65 on the far side of the dock with PN66 in the foreground. PN66’s complete transom and poop deck are being lifted over PN65 by the dock gantry crane. PN65’s accommodation block, completely fitted out with cabins, public spaces and wheelhouse equipment, will be lifted on before launch.

Sea trials and delivery of PN65 is scheduled for May. Four of the eight NewcastleMax series will deliver into service in 2012 and four in 2013.

AM

Monday, 12 December 2011

Capesize PN65 is a complete hull

Another really quick post on the progress of PN65 and PN66. PN65 is a complete vessel for the first time with the fitting of her bulbous bow.


Block for a sister ship is lifted over PN65


PN65 block comprising side shell, stool piece and bulkhead slotted in to No./No.2 Hold


Ready for lowering


Almost there


In position, ready for welding


Bulbous bow is lowered in to position and PN65 is a complete hull


PN65's Forecastle in the Paint Shop (upside down)


Sister-ship PN66 next to PN65 (Looking in to the Engine Room). Another identical Cape is in the dock ahead.

Photos courtesy of the Site Supervision Team

Tha Antipodean Mariner

Tuesday, 22 March 2011

Hull PN65 - The birth of a Capesize

Back to blogging after a long layoff (and a lot of guilt for not maintaining fresh material). With a view to keeping content 'fresh' for the next year or so, I'm blogging the birth of our first Capesize bulk carrier. The Antipodean Mariner's company went to the shipbuilding markets in late 2009 as the first glimmers of post-GFC recover were flickering. The container ship market was in complete meltdown, with ships being cancelled or deferred left, right and centre. Our requirement was for a series of Capesize bulkers for deployment in our iron ore and coal trades, and the 205,000 DWT NewcastleMax were assessed as best in class.

205,000 DWT Capesize

Developed by the Japanese yards for the domestic steel mills, these vessel can be regularly tracked alternating between the west and east Coast of Australia with iron ore and coking coal. The Yard which won the business had held a healthy order book of mega-container ships up until the 2009 crash. With the collapse of the financial structures behind these vessels, the cupboard was suddenly bare. The Yard turned to bulk carriers to maintain production at its facility and employment for its workforce.

HHIC-Phil Subic

The vessels will be 300m LOA by 50m beam and 18.4m summer draft. Electronically-controlled slow-speed diesel main engines have been specified for best performance under MARPOL Tier II regulations. The technical team managing the design process are incorporating features to make the vessels productive, easy to operate and a nice place to live and work.

PN065 cutting steel

Steel cutting for the first vessel, PN065, was in February and her progress will be reported regulary in this blog. PN065 is the first of eight identical vessels which will be built in a single dock. The first two will be laid down at the front of the dock and built side-by-side, with the second pair immediately behind them. As each pair are floated out, the pair behind will be floated forward and the next two
started. Sea trials and deliveries commence in 2011.

HHIC Subic dock

More to follow...

And by the way, I bought another bike for touring. The Street Triple is a hot 'point and shoot' but is a lonely trip without my pillion buddy.

BMW K1100LT

Antipodean Mariner
March 2011